NJORO FURNITURE MART LTD v TANZANIA ELECTRIC SUPPLY CO LTD 1995 TLR 205 (CA)
Court Court of Appeal - Arusha
Judge Nyalali CJ, Makame JJA and Kisanga JJA B
Civil Appeal No 39 of 1993
August 3, 1995
(From the decision of the High Court of Tanzania at Arusha, Munuo, J). C
Flynote
Tort - Damages - Whether to include an element to offset the effect of inflation and
devaluation.
Civil Practice and Procedure - Costs - Court awards half of the costs of the suit -
Whether proper. D
Civil Practice and Procedure - Interest - From date of filing suit to date of final
judgment - Interest on judgment debt.
-Headnote
The trial High court awarded a sum of Shs 728, 154/70/ = being part of the special E
damages claimed by the appellants, plus half of the costs of the suit and 10% interest
payable 'from the date of judgment to the date of final settlement'. The appellant
appealed to the Court of Appeal against the quantum of special damages awarded, half
of the costs of the suit without assigning any reasons, and failure of the Trial Judge to
award 'interest at bank rate on the decretal sum calculated from the date of filing the
suit to the date of final judgment'. The Court of Appeal upheld the quantum awarded
by the Trial Judge. On the other points raised: F
Held:
(i) Since in principle the quantum of damages has to be such as to restore
an injured party, as far as possible, to the position prior to the injury, it is correct in
law to include in the award of damages an element calculated to offset the effect of
inflation and devaluation; G
(ii) Costs follow the event; where the court directs that any costs shall not
follow the event the court shall state its reasons in writing.
(iii) It is apparent from the provisions of s 29 of the Civil Procedure Code,
H read together with rule 21 of Order 20 of the same code that interest is payable on
a judgment debt 'from the date of delivery of the judgment until the same shall be
satisfied', at the rate of seven percentum per annum or not exceeding twelve
percentum as agreed by the parties in writing or by consent;
(iv) The trial court was in error in making a direction for '10% interest
from the date of judgment to the date of final settlement' in the absence of agreement
by the parties; I
1995 TLR p206
NYALALI CJ
A (v) The appellant is entitled to interest at bank rate from the date of filing
the suit to date of delivery of judgment.
Case Infomation
Appeal allowed in part.
Case referred to:
B (1) Kioka Ltd v. De Angelis [1969] EA 7
Jonathan for the appellant.
Maro for the respondent.
[zJDz]Judgment
C Nyalali, CJ delivered the following considered judgment of the Court:
This is an appeal by Njoro Furniture Mart Ltd, hereinafter called the appellant,
against part of the judgment and decree of the High Court at Arusha where the
appellant had instituted a suit against Tanzania Electric Supply Co Ltd, hereinafter D
called the respondent. The suit was for payment of special and general damages
arising out of alleged negligent conduct on the part of the respondent, plus costs and
interest. The trial High Court, Munuo, J awarded a sum of Shs E 728,154/70/= being
part of the special damages claimed, plus half of the costs of the suit and 10 per cent
interest payable 'from the date of judgment to the date of final settlement'. The
remainder of appellant's claim was rejected by the High Court. Appellant was
aggrieved, hence this appeal to this court. Mr Jonathan, learned advocate, represents
the appellant in this appeal, whereas Mr Maro, F learned advocate, represents the
respondent. 12 grounds of appeal were submitted and argued in the appeal before us.
G It is common ground that on 17 September 1989 the carpentry workshop of the
appellant at Njoro, otherwise known as Maili Sita, in Moshi municipality was gutted
by fire some time after the respondent's employees had attended to the electricity line
and transformer serving the appellant's carpentry workshop. That fire also damaged
the property of the appellant's neighbours. Subsequently, at a meeting H held
between the respondent's representatives on one side and the appellant and its
neighbours on the other side, the respondent, through its representatives, admitted
liability and agreed to compensate the appellant and the neighbours for the damage
suffered. Prolonged negotiations and communications regarding the quantum of
damages took place between the appellant and the respondent without success. I
1995 TLR p207
NYALALI CJ
It is common ground also that in the course of the negotiations for settlement of A
claims, the respondent asked the appellant to give an estimate of the costs of repairing
the damaged workshop; and an estimate of the loss of profits suffered as a
consequence of the fire. In response to such requests, the appellant supplied to the
respondent various estimates as per Exh P2, P9 and D6. Exh P2 is an B estimate
prepared by a firm known as General Electric Service and signed by DW8 in respect
of costs for 'repair and replacement of damaged motors and electric installation ...'. It
is dated 18 January 1990 and puts the cost at Shs 1,261,808/=. Exh D6 is a similar
estimate by the same firm, that is General C Electric Service, and is dated 25 July
1991. Exh D6 puts the cost for 'electrical repair' of the workshop at Shs 728,154.70/=.
Exh P9 is an accountant's report prepared by one Anael Patrick Kavishe (PW3) of
Masawe & Co Ltd, a firm of accountants and auditors, showing that the appellant had
suffered loss of profits in the region of Shs 17,000,000/=. It is common ground that the
appellant is a usual D client of Masawe & Co Ltd, on retainership basis.
Furthermore, it is undisputed between the parties that in the course of attempting to
negotiate a settlement of the claims, the respondent also undertook its own E
investigations of the damage and loss suffered by the appellant. Towards that end, one
Mtoro Rajab Khalifan (DW6) prepared a report of the accounts of the appellant. That
report, admitted at the trial as Exh D7, showed that the carpentry workshop business
was running at a loss at the time of the fire incident. DW6 is a registered accountant
employed by the respondent. F
It is the appellant's case that it is entitled to be paid not only the sum of Shs
1,261,808/= as per Exh P2, being the cost of restoring the carpentry workshop to
normality, but the sum of Shs 17,105,394/= being the estimated loss of profits G
arising from loss of sales to customers. Furthermore, it is part of the appellant's case
that the appellant is entitled to be paid compensation for the loss likely to be suffered
as a result of action likely to be taken by appellant's customers for failure to supply
goods to the latter as agreed before the workshop was gutted by fire. Appellant
further contends that any compensation paid by the respondent should H include an
element to offset the effect of inflation and devaluation, plus interest at bank rate in
order to put the appellant in the position it would have been had the workshop
continued to operate.
The respondent's case on the other hand is to the effect that both estimates by the
appellant as per Exh P2 and P9 are at best unreli- I
1995 TLR p208
NYALALI CJ
A able. It is respondent's contention that the estimate of the cost of restoring the
workshop as shown in Exh P2 is fraudulent and grossly exaggerated. Furthermore,
respondent contends that the true financial position of the workshop at the time of
the fire incident is that it was a loss-making business as shown in Exh D7.
Furthermore, it was part of the respondent's case at the trial in the High B Court that
the appellant should have mitigated the damage by having the damaged workshop
machines repaired and installed by General Electric Service, the firm which was
apparently ready to repair and install the machines on credit.
C The first issue for consideration and decision in this case concerns the cost of
restoring appellant's workshop to the working conditions it had prior to being gutted
by fire. The only evidence relevant to decision of this issue is Exh P2 and D6. Both are
estimates prepared by the appellant. The learned Trial Judge disregarded Exh D P2
on the ground that the person who signed it, that is DW8, was not sure of its contents
as he claimed not to be conversant with the English language in which it was written.
The learned Trial Judge, however, accepted the contents of Exh D6 as being more
reliable and proceeded to award the sum shown therein that is Shs E 728,154/70/=.
Bearing in mind that Exh D6 is a document prepared and supplied by the appellant in
the course of negotiation to settle appellant's claims against the respondent, we find
no basis for faulting the learned Trial Judge in that regard. We therefore find, as she
did, that the cost of restoring the carpentry workshop to its working condition at the
time Exh D6 was prepared is Shs 728,154/70/=. F
The second issue for consideration and decision is whether the appellant suffered loss
of profits as a result of the fire. The learned Trial Judge does not appear to have
specifically considered this matter when dealing with the 11 issues framed G for
consideration by the trial court. Obviously the matter fell for consideration under
issue No 9, that is, 'Has the plaintiff suffered loss of income and if so, to what extent?'.
It would seem that the matter slipped from the attention of the learned Trial Judge
apparently because she confined herself to only one aspect of the H issue - that is,
appellant's alleged failure to mitigate damages. Obviously the issue of mitigation of
specific damages arises only where loss is proved.
In the present case the only evidence relevant to the issue of loss of profits is to be
found in the testimonies of PW3 and DW6 and the respective reports each prepared,
that is Exh P9 and D7 respectively. The testimonies and reports of these accountants
is diame- I
1995 TLR p209
NYALALI CJ
trically opposed to each other. One supports the contention that appellant's A
venture was profitable before it was closed down. The other supports the contrary
view that appellant's venture was making a loss at the material time. Unfortunately
neither PW3 nor DW6 is an independent witness, because the former is a retained
client who normally audits the appellant's accounts, and the latter is an employee of
the respondent. We think that under these circumstances, where the B burden of
proof is upon the appellant (as plaintiff in the case), the appellant has to show that
PW3 and his report are more reliable than DW6 and his report. It seems to us that
this was not done. It follows therefore that the appellant failed to prove on a balance
of probabilities that he suffered loss of profits. C
The third issue is whether the appellant is entitled to be paid compensation for loss
likely to be suffered as a result of claims likely to be made for failure to deliver goods
to clients as agreed before the workshop was gutted by fire. The learned D Trial
Judge found to the effect that the appellant had received confirmed orders for the
manufacture and supply of sundry goods to clients before the workshop was gutted by
fire. She however did not consider whether the appellant would suffer loss
consequent upon possible claims by those clients. In our considered opinion E it
seems that the appellant, on the evidence adduced at the trial, has a defence against
such possible claims. The obvious defence is that of frustration of contract arising out
of appellant's workshop being gutted by fire. It follows therefore that appellant is not
entitled to compensation for possible claims. F
The fourth issue is whether any amount of money awarded to the appellant as
damages should include an element to offset the effect of inflation and devaluation.
We think that since in principle the quantum of damages has to be such as to restore
an injured party, as far as possible to the position prior to the injury, it is correct in
law to include in the award of damages an element calculated to offset G the effect
of inflation and devaluation. As stated by Kemp and Mc Oustra, learned authors in
their The Quantum of Damages, vol 1, 2nd ed, 'leaving authority aside, both principle
and common sense require that the courts, when they H assess an award of money,
which is to compensate a plaintiff for the damage caused to him by his injuries,
should take into account large and comparatively permanent changes in real value,
i.e. in the purchasing power of money'. Unfortunately in the present case, though
appellant was represented by experienced counsel at the trial, no evidence or material
was adduced at the trial upon which the rate of inflation or I
1995 TLR p210
NYALALI CJ
A devaluation could be determined. We are therefore unable to award any amount
for inflation or devaluation.
The fifth and last issue before us is whether the trial court erred in awarding half of
the costs of the suit instead of granting the full costs, and whether it erred in
awarding interest at 10 per cent from the date of judgment to the date of payment, B
instead of granting interest at bank rate from date of filing the suit to date of payment
as prayed.
With regard to the matter of costs, Mr Maro, learned advocate for the respondent,
argued in the appeal before us that the trial court was correct in exercising its C
discretion by granting less than the full costs in favour of the appellant, on the ground
that the appellant had failed to prove a substantial part or the claim contained in the
plaint. Undoubtedly in our opinion, costs are within the discretion of the court as
stated under s 30 of the Civil Procedure Code, 1966. It has, D however, long been
established by the courts that costs normally follow the event. See case of Kiska Ltd v
De Angelis (1). Moreover, under ss (2) of s 30 of the Civil Procedure Code, it is
expressly stated that, 'Where the court directs that any costs shall not follow the
event, the court shall state its reasons in writing.' E
The gist of appellant's complaint is that the court did not state its reasons in writing
for directing only half of the costs to be paid. The complaint is justified. We have,
however, to ask ourselves what legal effect does this procedural error have? In our
considered opinion, since the reasons for awarding less than the full costs in F favour
of the appellant are so obvious, the error is curable. We thus cure the error by stating
that the appellant, who was the plaintiff in the trial court, is entitled to half the costs
of the suit by reason of failure to prove a substantial part of the claim.
G As to the matter of payment of interest, it is apparent from the provisions of s 29
of the Civil Procedure Code, read together with r 21 of Ord 20 of the same Code that
interest is payable on a judgment debt 'from the date of delivery of the judgment until
the same shall be satisfied.' Under r 21 of Ord 20, 'the rate ... shall H be seven per
cent per annum or such other rate, not exceeding 12 per cent per annum as the parties
may expressly agree in writing before or after the delivery of the judgment or as may
be adjudged by consent'.
It is thus evident that the trial court was in error in making a direction for '10 per
cent interest from the date of the judgment to the date of final settlement', in the
absence of agreement by the I
1995 TLR p211
NYALALI CJ
parties. We are bound to intervene to correct this error. But before we do so, we A
have to consider whether the appellant should be paid any interest for the period
prior to judgment. Under s 29 of the Civil Procedure Code, a court has power '... to
order interest to be paid up to the date of judgment at such rates as it may deem
reasonable ...'. The appellant had claimed in the plaint, 'interest at bank rate on the B
decretal sum calculated from the date of filing the suit to the date of final judgment.'
We think under the circumstances of this case, the claim is fully justified. The
appellant is entitled to interest at bank rate from the date of filing the suit to date of
delivery of judgment. C
In the final analysis therefore, this appeal partly fails and partly succeeds to the extent
that the appeal against the principal sum and costs filed, but the appeal against the
order for payment of interest succeeds to the extend indicated above. Under the
circumstances of this case, we think it is just that appellant be paid one-third of the
costs of this appeal. D
1995 TLR p211
F
0 Comments
PLACE YOUR COMMENT HERE
WARNING: DO NOT USE ABUSIVE LANGUAGE BECAUSE IT IS AGAINST THE LAW.
THE COMMENTS OF OUR READERS IS NOT OUR RESPONSIBILITY.