Recent Posts

6/recent/ticker-posts

“200”, Aptitude Test Questions and Answers for Tutorial Assistant (Quantity Surveyor)– Mbeya University of Science and Technology.



“200”, Aptitude Test Questions and Answers for Tutorial Assistant (Quantity Surveyor)– Mbeya University of Science and Technology..

 

 

This compilation of 200 multiple-choice questions is designed to assist candidates preparing for the Tutorial Assistant (Quantity Surveying) public service aptitude test. The questions cover essential areas including quantity surveying principles, construction measurement, contract administration, tendering processes, cost control, and project management. Each question is accompanied by a set of closely related answer choices to simulate the actual test environment and enhance critical thinking skills. Detailed rationales for each answer provide clarity and deepen understanding. This resource aims to build the candidate’s competence and confidence, ensuring readiness for the diverse challenges of the selection process.

 

Prepared by:

Quantity Surveyor, compiled by

Johnson Yesaya Mgelwa.

A lawyer stationed in Dar-es-salaam.

0628729934.

Date: July 19, 2025

 

Dear applicants,

This collection of questions and answers has been carefully prepared to help all of you to understand the key areas tested during the interview. The goal is to provide a useful, and practical study guide so you can all perform confidently and fairly in the selection process. I wish you the best of luck, and may this resource support you in achieving success!

 

Warm regards,

Johnson Yesaya Mgelwa

 

For Personal Use by Applicants Preparing for Quantity Surveyor interview at Public Service Recruitment Service.

ALL QUESTIONS ARE COMPILED TOGETHER.

1. Which of the following best describes the main role of a Bill of Quantities in construction projects?

A. To provide structural designs and material strength analysis B. To estimate and control costs during construction C. To prepare architectural designs and drawings D. To evaluate contractor’s performance

Answer: B

Rationale: The Bill of Quantities (BOQ) is a document prepared to provide project cost estimation, serve as a basis for tendering, and facilitate cost control during construction. It itemizes materials, parts, and labor with their costs.


2. What is the main purpose of a feasibility study in quantity surveying?

A. To ensure the building design is aesthetically appealing B. To assess the financial and technical viability of a project C. To create the structural drawings and foundation plans D. To verify land ownership before acquisition

Answer: B

Rationale: A feasibility study evaluates the practicality of a proposed project in terms of economic, legal, technical, and scheduling factors. Quantity surveyors use it to assess whether a project is financially and technically viable before it proceeds.


3. Which of the following is NOT typically a duty of a quantity surveyor during the post-contract stage?

A. Preparing final account statements B. Monitoring construction progress C. Preparing tender documentation D. Managing cost control on site

Answer: C

Rationale: Preparing tender documentation is part of the pre-contract stage, where the contract sum and scope are defined. In the post-contract stage, quantity surveyors focus more on cost control, progress monitoring, and final account preparation.


4. Which standard method is commonly used for measuring building works in Tanzania?

A. CESMM B. NRM C. SMM7 D. ARM3

Answer: A

Rationale: The Civil Engineering Standard Method of Measurement (CESMM) is widely used in Tanzania for civil engineering works, especially in public sector projects. It provides a standard approach to quantify and price construction work.


5. Which document typically defines the scope of work and obligations between the employer and contractor?

A. Project Feasibility Report B. Contract Agreement C. Procurement Plan D. Construction Program

Answer: B

Rationale: The contract agreement is a legal document that outlines the scope of work, responsibilities, timelines, and financial arrangements between the employer and the contractor, making it essential for project execution.


6. Which of the following best defines a provisional sum in a Bill of Quantities?

A. A fixed payment for all project costs B. An estimate for undefined or unforeseen work C. A final settlement amount D. The contractor’s profit margin

Answer: B

Rationale: A provisional sum is an estimated amount included in the BOQ to cover work or services that are not fully defined at the time of tendering. It provides flexibility to include additional scope as needed.


7. In construction contracts, the term ‘practical completion’ refers to:

A. When 50% of the work is done B. When defects are still being corrected C. When the works are complete and usable D. When payments are fully settled

Answer: C

Rationale: Practical completion marks the point when construction is completed and the building can be used, though minor defects may remain. It triggers handover and stops the contractor's liability for delays.


8. What is the key role of a Quantity Surveyor in tender evaluation?

A. Approving building permits B. Supervising design engineers C. Assessing and comparing financial bids D. Approving payments to consultants

Answer: C

Rationale: During tender evaluation, quantity surveyors analyze and compare the submitted bids for accuracy, compliance, and value for money to recommend the most economically advantageous offer.


9. What is typically included in pre-tender estimates?

A. As-built drawings B. Post-contract reports C. Forecasted project costs D. Actual construction expenses

Answer: C

Rationale: Pre-tender estimates provide forecasted costs of a project before tendering begins, helping clients budget and assess affordability.


10. Which of the following software is widely used in quantity surveying for cost estimation and BOQ preparation?

A. AutoCAD B. Microsoft Word C. CostX D. SketchUp

Answer: C

Rationale: CostX is specialized software for quantity surveying, used to generate cost estimates and prepare digital BOQs from 2D and 3D drawings.


11. Which of the following is NOT a method of procurement in construction?

A. Design and Build B. Traditional Contract C. Time-Based Consulting D. Management Contracting

Answer: C

Rationale: Time-based consulting is a consultancy engagement method, not a procurement method. The other options are standard construction procurement routes.


12. A prime cost sum in a BOQ usually refers to:

A. Payment to subcontractors only B. Materials to be selected by the client C. Site supervisory charges D. Final account settlement

Answer: B

Rationale: A prime cost sum is an allowance in the BOQ for materials or services where exact details are not known at tender time, typically to be chosen by the client later.


13. Which principle of measurement emphasizes consistency and standardization across BOQs?

A. Flexibility B. Accuracy C. Uniformity D. Complexity

Answer: C

Rationale: Uniformity ensures that BOQs are prepared in a consistent format, making them easier to interpret, compare, and evaluate fairly across all bidders.


14. Which construction contract clause typically addresses delays and time extensions?

A. Termination Clause B. Defects Liability Clause C. Liquidated Damages Clause D. Extension of Time Clause

Answer: D

Rationale: The Extension of Time clause outlines the process and grounds for granting additional time due to delays beyond the contractor’s control.


15. Which of the following is most critical when preparing a project cash flow forecast?

A. The contractor’s profit margin B. Labour skills C. Payment schedule and project timeline D. Soil test results

Answer: C

Rationale: A project cash flow forecast depends heavily on the payment schedule and timeline, which determines when funds will be required or received.


16. In Tanzania, which Act governs the registration and regulation of Quantity Surveyors?

A. Land Act B. Contractors Registration Act C. Architects and Quantity Surveyors (Registration) Act D. Public Procurement Act

Answer: C

Rationale: The Architects and Quantity Surveyors (Registration) Act establishes the Architects and Quantity Surveyors Registration Board (AQRB) which regulates the profession in Tanzania.


17. Which of the following is a key advantage of the Design and Build procurement method?

A. Separate contracts for design and construction B. Longer project delivery time C. Single point responsibility for client D. More variation orders

Answer: C

Rationale: Design and Build offers a single point of responsibility for both design and construction, which can reduce disputes and improve efficiency.


18. Retention money in construction contracts serves to:

A. Increase contractor profit B. Cover consultant fees C. Ensure defects are corrected D. Reduce tax liability

Answer: C

Rationale: Retention is a portion of payment withheld to ensure the contractor fixes any defects during the defects liability period after completion.


19. Which of the following is a form of tendering used in public sector projects in Tanzania?

A. Direct Negotiation B. Selective Tendering C. Random Tendering D. Informal Auctioning

Answer: B

Rationale: Selective tendering is commonly used in public projects to invite bids from pre-qualified contractors, ensuring competition among competent bidders.

20. What does value engineering primarily aim to achieve?

A. Increase material usage B. Reduce staff salaries C. Optimize project cost without affecting quality D. Delay project timelines

Answer: C

Rationale: Value engineering is a systematic method of improving the value of a project by analyzing its functions to reduce cost while maintaining or improving quality.


21. Which construction cost category includes items such as permits, fees, and legal costs?

A. Direct costs B. Contingency costs C. Preliminary costs D. Indirect costs

Answer: D

Rationale: Indirect costs are expenses not directly tied to the physical construction but necessary for the project, such as permits, legal fees, and administration.


22. What is the purpose of a site visit before preparing a BOQ?

A. To interview workers B. To supervise excavation C. To understand site conditions D. To approve structural designs

Answer: C

Rationale: A site visit helps the quantity surveyor understand the location, access, soil, and constraints which influence pricing, methods, and BOQ accuracy.


23. Which clause in standard forms of contract covers dispute resolution procedures?

A. Warranty clause B. Variation clause C. Dispute clause D. Force majeure clause

Answer: C

Rationale: The dispute clause outlines the procedure for resolving disagreements, including mediation, adjudication, arbitration, or litigation.


24. Which of the following would best help a client assess contractor capability before awarding a contract?

A. Checking weather forecasts B. Reviewing contractor’s past project portfolio C. Asking neighbors D. Sending unsolicited offers

Answer: B

Rationale: Reviewing a contractor’s experience, portfolio, and financial capability helps the client assess reliability and competence before award.


25. What is the primary purpose of a Gantt chart in project management?

A. Budget analysis B. Cost planning C. Schedule visualization D. Materials procurement

Answer: C

Rationale: A Gantt chart is used to visually represent the project schedule, showing task durations, start and end dates, and dependencies.


26. In the context of construction, what does the term “variation” mean?

A. Construction mistake B. Change in work scope C. Quality control process D. Material wastage

Answer: B

Rationale: A variation is an official change to the work originally agreed in the contract, which may affect cost, time, or specifications.


27. The abbreviation “FIDIC” refers to:

A. Federal Infrastructure Design Institute Council B. Finance for International Design and Construction C. International Federation of Consulting Engineers D. Foreign Investment and Design in Construction

Answer: C

Rationale: FIDIC stands for Fédération Internationale Des Ingénieurs-Conseils (International Federation of Consulting Engineers), which publishes widely used standard contracts.


28. The contingency sum in a budget is mainly included to cover:

A. Client entertainment B. Project promotion costs C. Unforeseen costs D. Final payment bonuses

Answer: C

Rationale: Contingency sums are allowances in the budget for unexpected or unpredictable expenses that may arise during construction.


29. What is the role of a consultant quantity surveyor during a project?

A. Issuing land titles B. Inspecting food for workers C. Advising on cost and contract issues D. Supervising electrical installations

Answer: C

Rationale: Consultant quantity surveyors offer cost advice, contract administration, valuations, and financial reporting on behalf of the client.


30. What is the purpose of retention in a construction contract?

A. Reward performance B. Penalize late workers C. Guarantee defect correction D. Reduce taxes

Answer: C

Rationale: Retention ensures the contractor returns to fix defects during the defect liability period by withholding part of their payment.


 

📘 Get the Full Aptitude Test PDF (Questions 31–200)

You’ve just accessed the first 30 questions. The full set of 200 expertly prepared aptitude test questions for the Quantity Surveyor – MUST is available, pay and get access.

To get access of the full PDF through your Gmail (Questions 31–200), please make a payment of Tsh 10,000 to the LIPA numbers below:

Airtel Money LIPA Number: 13970429
M-Pesa Withdrawal code:  826910
Registered Name: Johnson Yesaya Mgelwa

After payment, please send a text message with the words “Quantity Surveyor” to:

Contact Number: +255 628 729 934

⚠️ Important Notice

  • The PDF will be watermarked with your name and phone number and protected for personal use only.
  • Redistribution, sharing, screenshotting, or copying the contents is strictly prohibited. When you share unlawfully, your name and phone number are visible and easy to trace that you leaked a document to other third parties.
  • Legal action may be taken against the misuse of this material.

Thank you for supporting quality content. Best of luck in your interview preparation!

Post a Comment

0 Comments