“200”, Aptitude Test
Questions and Answers for Mkaguzi Daraja la II Fani ya Uhandisi wa
Umeme (Electrical Engineering) at –
the National Audit Office (NAOT).
ABSTRACT
This material contains 200 carefully
developed multiple-choice questions and answers for candidates preparing
for the Public Service Online Aptitude Test for Mkaguzi Daraja la II Fani
ya Uhandisi wa Umeme – Electrical Engineering (NAOT) in Tanzania. The
questions focus on audit of public power projects, integrating
electrical engineering principles with audit judgment, risk assessment, and
performance evaluation. Designed to reflect the analytical and closely
related answer structure of real exams, the set strengthens candidates’
ability to reason, analyze, and apply knowledge in public-sector audit
contexts, thereby improving overall exam readiness and chances of success.
Prepared by: Electrical Engineers
Compiled by Johnson Yesaya Mgelwa.
A lawyer stationed in Dar-es-salaam.
0628729934.
Date: June 1, 2025
Dear applicants,
This collection of questions and answers
has been prepared to help all of you to understand the key areas tested during
the interview. The goal is to provide a useful, and practical study guide so you
can all perform confidently and fairly in the selection process. I wish you the
best of luck, and may this resource support you in achieving success!
Warm regards,
Johnson Yesaya Mgelwa
For Personal Use by Applicants Preparing
for Mkaguzi Daraja la II Fani ya Uhandisi wa Umeme (Electrical Engineering) at
– the National Audit Office (NAOT).
ALL QUESTIONS ARE COMPILED TOGETHER.
QUESTION 1
During the planning phase of an audit for
a government-funded power substation project, which activity MOST appropriately
supports risk-based audit coverage?
A. Reviewing contractor staff
qualifications
B. Identifying high-value and high-risk project components
C. Inspecting all installed equipment equally
D. Verifying availability of operational manuals
Answer: B
Rationale:
Risk-based auditing prioritizes areas with higher financial exposure, technical
complexity, or likelihood of misstatement. In power projects, identifying
high-value and high-risk components such as transformers, switchgear, and
transmission lines allows auditors to allocate resources effectively. Reviewing
staff qualifications and manuals is useful but secondary, while inspecting all
components equally undermines risk prioritization.
QUESTION 2
An auditor finds that a public power
project experienced repeated design modifications after construction had begun.
What is the MOST appropriate audit concern arising from this situation?
A. Increased routine maintenance
requirements
B. Possible weaknesses in initial feasibility and planning
C. Improved adaptability to environmental conditions
D. Compliance with procurement procedures
Answer: B
Rationale:
Frequent design changes after construction indicate potential deficiencies in
initial feasibility studies, needs assessment, or technical planning. Such
weaknesses may lead to cost overruns, delays, and compromised project
objectives. While adaptability may appear positive, it does not justify poor
upfront planning in public infrastructure projects.
QUESTION 3
Which audit evidence BEST supports
verification that electrical equipment procured for a public power project
meets required technical specifications?
A. Supplier reputation records
B. Payment vouchers and invoices
C. Factory test certificates and inspection reports
D. Project progress meeting minutes
Answer: C
Rationale:
Factory test certificates and inspection reports provide direct, technical
assurance that equipment conforms to specified standards and performance
requirements. Invoices and supplier reputation are supporting documents but do
not confirm technical compliance. Meeting minutes reflect discussions rather
than verifiable compliance evidence.
QUESTION 4
In auditing a rural electrification
project, which factor MOST significantly affects the assessment of project
economy?
A. Distance between substations
B. Cost per household connected
C. Voltage regulation method used
D. Number of transformers installed
Answer: B
Rationale:
Economy focuses on minimizing costs while maintaining required quality. In
rural electrification, cost per household connected directly measures whether
public funds were used efficiently relative to output. Technical choices affect
performance but do not alone determine economic efficiency.
QUESTION 5
An audit team is assessing delays in
commissioning a public power plant. Which documentation is MOST critical to
establish responsibility for the delays?
A. Approved project implementation
schedule
B. Electrical drawings and schematics
C. Equipment maintenance manuals
D. Environmental impact assessment report
Answer: A
Rationale:
The approved project implementation schedule defines planned timelines,
milestones, and responsibilities. Comparing actual progress against this
baseline enables auditors to attribute delays accurately. Technical drawings
and manuals do not address timing accountability.
QUESTION 6
Which audit approach is MOST suitable
when evaluating whether a public power project achieved its intended
operational objectives?
A. Compliance audit
B. Financial audit
C. Performance audit
D. Procurement audit
Answer: C
Rationale:
Performance audits assess economy, efficiency, and effectiveness in achieving
intended objectives. Evaluating whether a power project delivers reliable
electricity as planned falls squarely under performance auditing rather than
financial or compliance-focused reviews.
QUESTION 7
When reviewing feasibility studies for a
government-funded transmission line, which assumption requires the MOST
critical scrutiny?
A. Forecasted electricity demand growth
B. Contractor profit margin estimates
C. Brand of transmission towers
D. Color coding of conductors
Answer: A
Rationale:
Demand growth projections directly affect capacity sizing, financial viability,
and long-term usefulness of the transmission line. Overestimated demand can
lead to underutilized assets, while underestimation may cause capacity
shortages. Other options have limited strategic impact.
QUESTION 8
An auditor notes that acceptance testing
of installed transformers was conducted without independent supervision. What
is the PRIMARY audit risk?
A. Increased transformer noise levels
B. Reduced equipment lifespan
C. Potential acceptance of non-compliant equipment
D. Higher electricity losses
Answer: C
Rationale:
Lack of independent supervision during acceptance testing increases the risk
that equipment not meeting specifications is approved for use. While
performance issues may follow, the immediate audit concern is the reliability
of acceptance and compliance assurance.
QUESTION 9
Which indicator BEST demonstrates
efficiency in the execution of a public power distribution project?
A. Total project budget size
B. Number of contractors engaged
C. Timely completion within approved cost
D. Frequency of site meetings
Answer: C
Rationale:
Efficiency relates to achieving outputs using minimum resources and time.
Completing the project on schedule and within budget reflects effective
resource utilization. Budget size and meetings alone do not measure efficiency.
QUESTION 10
During data analysis, an auditor observes
that actual energy losses in a new distribution network exceed design
estimates. What is the MOST appropriate audit focus?
A. Consumer billing accuracy
B. Network design and installation quality
C. Electricity tariff structure
D. Staff attendance records
Answer: B
Rationale:
Higher-than-expected energy losses suggest issues in network design, conductor
sizing, installation practices, or equipment quality. These technical aspects
directly affect system performance and should be the primary audit focus.
QUESTION 11
Which source of evidence is MOST reliable
when verifying quantities of electrical materials installed in a public
project?
A. Contractor progress reports
B. Store issue vouchers
C. Physical site inspection records
D. Informal engineer confirmations
Answer: C
Rationale:
Physical site inspections provide direct, independent verification of installed
quantities. Contractor reports and vouchers support documentation but may not
reflect actual installation, while informal confirmations lack audit
reliability.
QUESTION 12
In auditing procurement of generators for
a public hospital, which criterion MOST directly relates to effectiveness?
A. Lowest purchase price
B. Delivery timeline compliance
C. Procurement approval signatures
D. Fuel consumption rate under load
Answer: D
Rationale:
Effectiveness concerns whether the generator performs its intended function
reliably and adequately. Fuel efficiency under load affects operational
sustainability and service delivery, making it a key effectiveness indicator.
QUESTION 13
Which audit finding MOST strongly
indicates weak internal controls in the management of a public electrical
project?
A. Minor deviations in cable routing
B. Lack of segregation between supervision and certification roles
C. Delays due to adverse weather
D. Changes in exchange rates
Answer: B
Rationale:
Failure to segregate supervision and certification responsibilities increases
the risk of errors, fraud, or biased approvals. Environmental and economic
factors may affect projects but do not directly reflect internal control
weaknesses.
QUESTION 14
When auditing a power project funded
through multiple fiscal years, what is the MOST critical audit concern?
A. Uniformity of technical standards
B. Availability of spare parts
C. Contractor staff turnover
D. Continuity of project objectives and funding
Answer: D
Rationale:
Multi-year projects risk changes in funding priorities and objectives, which
can affect completion and value for money. Ensuring continuity safeguards
project viability and accountability.
QUESTION 15
Which audit procedure BEST confirms that
public funds were used only for approved electrical project activities?
A. Comparing bank statements with design
drawings
B. Matching expenditures with approved work plans
C. Reviewing contractor safety training records
D. Inspecting installed equipment labels
Answer: B
Rationale:
Matching expenditures against approved work plans ensures that spending aligns
with authorized activities. Other procedures provide supporting information but
do not directly confirm budgetary compliance.
QUESTION 16
An auditor reviewing commissioning
reports notices incomplete load testing results. What is the MOST appropriate
audit implication?
A. Minor documentation oversight
B. Increased likelihood of billing disputes
C. Risk of operational failure under real conditions
D. Improved equipment flexibility
Answer: C
Rationale:
Incomplete load testing undermines assurance that the system can operate safely
and reliably under expected demand. This poses a significant operational and
public service risk.
QUESTION 17
Which factor MOST justifies re-auditing a
completed public power project?
A. Change in management personnel
B. Emergence of significant post-commissioning failures
C. Introduction of new electrical standards
D. Completion of defect liability period
Answer: B
Rationale:
Significant operational failures after commissioning indicate potential
deficiencies in design, construction, or oversight, justifying re-audit to
determine root causes and accountability.
QUESTION 18
When assessing value for money in a solar
power project, which comparison is MOST relevant?
A. Solar panel color variations
B. Cost per kilowatt installed versus output achieved
C. Number of site visits conducted
D. Duration of procurement process
Answer: B
Rationale:
Comparing cost per kilowatt installed with actual energy output directly links
expenditure to performance, enabling a meaningful value-for-money assessment.
QUESTION 19
Which audit evidence BEST supports
conclusions about sustainability of a public electrical project?
A. Initial capital cost estimates
B. Supplier delivery records
C. Contractor warranty period
D. Availability of trained operation and maintenance staff
Answer: D
Rationale:
Long-term sustainability depends on the ability to operate and maintain the
system effectively. Availability of trained personnel ensures continued
functionality beyond project completion.
QUESTION 20
An auditor finds that spare parts were
not included in the initial procurement of power equipment. What is the PRIMARY
audit concern?
A. Increased initial capital cost
B. Potential future operational disruptions
C. Non-compliance with procurement law
D. Delayed project commissioning
Answer: B
Rationale:
Absence of spare parts planning increases the risk of prolonged outages and
reduced system reliability, undermining project effectiveness and service
continuity.
QUESTION 21
Which factor MOST enhances reliability of
audit conclusions in technical power project audits?
A. Large sample sizes only
B. Detailed narrative reporting
C. Frequent management briefings
D. Use of independent technical experts
Answer: D
Rationale:
Independent technical experts strengthen audit conclusions by providing
objective, specialized analysis of complex electrical systems, reducing
reliance on management assertions.
QUESTION 22
In auditing contractor performance, which
indicator MOST directly reflects technical competence?
A. Compliance with reporting deadlines
B. Adherence to approved electrical standards
C. Number of staff employed
D. Length of contract period
Answer: B
Rationale:
Compliance with electrical standards demonstrates the contractor’s technical
ability to meet required specifications, directly reflecting competence.
QUESTION 23
Which situation MOST warrants
classification as a high audit risk in a public power project?
A. Slight variations in material brands
B. Routine design clarifications
C. Seasonal fluctuations in workload
D. Concentration of procurement decisions in one individual
Answer: D
Rationale:
Concentration of decision-making authority increases the risk of error, bias,
or misuse of funds, making it a significant audit risk indicator.
QUESTION 24
When analyzing audit data, which method
BEST supports identification of systemic weaknesses?
A. Isolated case review
B. Trend analysis across multiple projects
C. One-time site inspection
D. Random anecdotal evidence
Answer: B
Rationale:
Trend analysis across projects reveals recurring patterns and systemic issues
that isolated reviews may miss, strengthening audit insights.
QUESTION 25
Which audit conclusion is MOST
appropriate when a public power project meets technical specifications but
fails to deliver expected service levels?
A. The project is fully successful
B. Only financial controls were weak
C. Effectiveness objectives were not achieved
D. Procurement procedures were invalid
Answer: C
Rationale:
Meeting technical specifications alone does not guarantee effective service
delivery. Failure to achieve expected service levels indicates shortcomings in
effectiveness, a core audit criterion.
QUESTION 26
During an audit of a public power
distribution project, the auditor observes that load forecasts were revised
downward after procurement of major equipment. What is the MOST significant
audit implication?
A. Improved system flexibility
B. Potential overinvestment in capacity
C. Enhanced voltage stability
D. Increased equipment redundancy
Answer: B
Rationale:
Downward revision of load forecasts after procurement suggests that equipment
capacity may exceed actual demand, leading to inefficient use of public funds.
This raises concerns about planning accuracy and value for money rather than
technical performance improvements.
QUESTION 27
Which audit procedure BEST supports
verification that a public power project complied with approved technical
designs during construction?
A. Comparing as-built drawings with
approved designs
B. Reviewing contractor payroll records
C. Examining site safety meeting minutes
D. Confirming delivery notes for materials
Answer: A
Rationale:
Comparing as-built drawings with approved designs directly confirms whether
construction adhered to authorized technical specifications. Other documents
provide indirect or administrative information but do not validate design
compliance.
QUESTION 28
In assessing effectiveness of a
government-funded transmission project, which outcome is MOST relevant?
A. Number of inspection visits conducted
B. Frequency of coordination meetings
C. Amount of contingency funds unused
D. Reduction in transmission outages
Answer: D
Rationale:
Effectiveness focuses on achievement of intended outcomes. Reduced transmission
outages demonstrate that the project successfully improved system reliability,
which is a core objective of transmission investments.
QUESTION 29
An auditor notes that contract variations
significantly increased project cost without proportional scope expansion. What
is the PRIMARY audit concern?
A. Improved technical innovation
B. Weak change management controls
C. Compliance with environmental safeguards
D. Increased contractor accountability
Answer: B
Rationale:
Cost increases without corresponding scope changes indicate weaknesses in
change control, approval processes, or cost justification, posing risks to
financial discipline and value for money.
QUESTION 30
Which evidence MOST reliably confirms
that installed electrical equipment is suitable for local operating conditions?
A. Manufacturer marketing brochures
B. Equipment nameplates
C. Site-specific commissioning test results
D. Supplier delivery schedules
Answer: C
Rationale:
Commissioning tests conducted under actual site conditions demonstrate whether
equipment performs as required in the local environment. Brochures and
nameplates do not verify real operational suitability.
📘 Get the Full Aptitude Test Questions PDF through your Gmail (Questions 1–200)
You’ve just accessed the first 30 questions. The full set of 200 expertly prepared Aptitude Test questions for Mkaguzi Daraja la II Fani ya Uhandisi wa Umeme (Electrical Engineering) at – the National Audit Office (NAOT). Is available, pay, and get access.
To get access to the full PDF, please make a payment of Tsh 10,000 to the LIPA numbers below:
After payment, please send a text message to notify us of your payment:
⚠️ Important Notice
- The PDF will be watermarked with your name and phone number and protected for personal use only.
- Redistribution, sharing, screenshotting, or copying the contents is strictly prohibited. When you share unlawfully, your name and phone number are visible and easy to trace as you leaked a document to other third parties.
- Legal action may be taken against the misuse of this material.
Thank you for supporting quality content. Best of luck in your interview preparation!
%20at%20%E2%80%93%20the%20National%20Audit%20Office%20(NAOT)..png)
0 Comments
PLACE YOUR COMMENT HERE
WARNING: DO NOT USE ABUSIVE LANGUAGE BECAUSE IT IS AGAINST THE LAW.
THE COMMENTS OF OUR READERS IS NOT OUR RESPONSIBILITY.