“200”, Aptitude Test Questions and Answers for Afisa Manunuzi Daraja la II (Procurement Officer II) at Air Tanzania Company Limited – ATCL.

 


“200”, Aptitude Test Questions and Answers for Afisa Manunuzi Daraja la II (Procurement Officer II) at Air Tanzania Company Limited – ATCL.

 

ABSTRACT

This material contains 200 carefully prepared multiple-choice questions designed to help candidates prepare effectively for the Procurement Officer II written interview at Air Tanzania Company Limited (ATCL). The questions are practical and scenario-based, reflecting how procurement is actually handled in public institutions and in an airline environment. Each question includes a clear answer and a well-explained rationale to help candidates understand the reasoning behind the correct choice, not just memorize facts. The content covers procurement planning, tendering, evaluation, contract management, ethics, risk control, and compliance with Tanzanian public procurement laws, making it a reliable and easy-to-use revision guide for candidates from different academic backgrounds.

 

Prepared by: Procurement Officer II

Compiled by Johnson Yesaya Mgelwa.

A lawyer stationed in Dar-es-salaam.

0628729934.

Date: June 1, 2025

 

Dear applicants,

This collection of questions and answers has been prepared to help all of you to understand the key areas tested during the interview. The goal is to provide a useful, and practical study guide so you can all perform confidently and fairly in the selection process. I wish you the best of luck, and may this resource support you in achieving success!

 

Warm regards,

Johnson Yesaya Mgelwa

 

For Personal Use by Applicants Preparing for Afisa Manunuzi Daraja la II (Procurement Officer II) at Air Tanzania Company Limited – ATCL.

ALL QUESTIONS ARE COMPILED TOGETHER.

1. At ATCL, which activity BEST reflects the role of a Procurement Officer II in the procurement cycle?

A. Assisting in preparation and issuance of approved tender documents
B. Making final procurement award decisions
C. Approving payments to suppliers
D. Negotiating international aviation treaties

Answer: A

Rationale: Procurement Officer II operates at an operational and support level, where responsibilities include preparing and issuing approved tender documents and maintaining records, while final approvals and awards remain with higher authority levels to preserve accountability and segregation of duties.


2. Why is compliance with the approved Annual Procurement Plan (APP) important in a public entity like ATCL?

A. It allows emergency procurement without justification
B. It ensures procurement activities align with budgeted and approved needs
C. It replaces the need for procurement regulations
D. It limits supplier participation

Answer: B

Rationale: The APP links procurement activities to approved budgets and organizational needs, ensuring transparency, control of public resources, and compliance with public procurement laws, which is critical for audit and accountability purposes.


3. In public procurement, which principle MOST directly promotes fair competition among suppliers?

A. Confidential negotiations
B. Supplier pre-selection
C. Equal access to information and clear evaluation criteria
D. Preference for incumbent suppliers

Answer: C

Rationale: Fair competition is achieved when all bidders receive the same information and are evaluated using pre-disclosed criteria, preventing bias and ensuring procurement decisions are based on merit rather than influence or familiarity.


4. Which situation presents the GREATEST procurement risk for ATCL?

A. Awarding contracts without proper documentation
B. Maintaining procurement records
C. Conducting market price analysis
D. Using standardized tender documents

Answer: A

Rationale: Awarding contracts without proper documentation undermines transparency, weakens audit trails, exposes the organization to legal challenges, and increases the risk of fraud or value-for-money losses.


5. Why is segregation of duties important in procurement operations?

A. To increase speed of procurement
B. To reduce supplier participation
C. To centralize authority
D. To prevent fraud and conflict of interest

Answer: D

Rationale: Segregation of duties ensures that no single officer controls all stages of procurement, reducing opportunities for fraud, errors, and abuse of power while strengthening internal controls.


6. In a public airline like ATCL, why must procurement planning be directly linked to the approved budget?

A. To ensure procurement commitments do not exceed authorized financial limits
B. To reduce the number of procurement staff involved
C. To eliminate the need for procurement approvals
D. To speed up supplier selection

Answer: A

Rationale: Linking procurement planning to the approved budget ensures that commitments are lawful, affordable, and aligned with financial controls, preventing unauthorized expenditure and audit queries.


7. ATCL urgently requires aircraft spare parts after an unexpected technical fault grounds an aircraft. As a Procurement Officer II, what should be your FIRST action?

A. Confirm whether the situation qualifies for emergency procurement and document justification
B. Contact the nearest supplier and place an order immediately
C. Bypass procurement procedures to avoid delays
D. Request suppliers to submit quotations informally

Answer: A

Rationale: Even in urgent situations, the first responsibility is to establish and document whether the situation legally qualifies as an emergency, ensuring subsequent actions remain compliant and auditable.


8. When receiving goods from a supplier, what should a Procurement Officer II verify FIRST?

A. Supplier reputation
B. Invoice payment schedule
C. Quantity and quality against delivery documents
D. Contract extension options

Answer: C

Rationale: Verification of quantity and quality ensures that delivered goods conform to contractual specifications before acceptance, protecting the organization from losses due to shortages, defects, or non-compliance.


9. Which action BEST supports value for money in procurement?

A. Selecting the lowest-priced bid automatically
B. Favoring long-term suppliers
C. Ignoring delivery timelines
D. Evaluating cost, quality, and delivery reliability together

Answer: D

Rationale: Value for money is achieved by balancing cost with quality and delivery performance, ensuring the organization receives goods or services that meet operational needs sustainably rather than focusing on price alone.


10. During bid evaluation, you notice that one bidder failed to submit a mandatory document required in the tender. What is the MOST appropriate action?

A. Declare the bid non-responsive and exclude it from further evaluation
B. Request the bidder to submit the missing document
C. Ignore the omission to promote competition
D. Deduct marks during financial evaluation

Answer: A

Rationale: Failure to meet mandatory requirements renders a bid non-responsive and it must be excluded to preserve fairness and compliance with procurement rules.


11. Why is PSPTB registration required for procurement professionals in Tanzania?

A. To replace academic qualifications
B. To authorize payment approvals
C. To confirm professional competence and ethical accountability
D. To allow direct negotiation with suppliers

Answer: C

Rationale: Registration with PSPTB ensures procurement officers meet professional standards, adhere to ethical codes, and are accountable to a regulatory body, strengthening integrity in public procurement.


12. What is the MAIN objective of stock taking in an organization like ATCL?

A. Adjusting supplier prices
B. Verifying physical stock against records
C. Planning flight schedules
D. Training store personnel

Answer: B

Rationale: Stock taking confirms whether physical inventory matches recorded data, helping identify discrepancies, prevent losses, and ensure accurate financial and operational reporting.


13. In procurement planning, why is market analysis important?

A. To eliminate competition
B. To delay procurement
C. To understand price trends and supplier capacity
D. To justify single sourcing automatically

Answer: C

Rationale: Market analysis helps procurement officers understand prevailing prices, availability, and supplier capabilities, enabling realistic cost estimates and informed procurement decisions.


14. After contract award, a supplier proposes changing specifications claiming “equivalent performance.” What should guide your response?

A. Assess whether the change affects scope, cost, and contract objectives before approval
B. Accept the change to maintain supplier relationship
C. Reject automatically without review
D. Allow the supplier to proceed informally

Answer: A

Rationale: Any proposed change must be assessed for its impact and approved formally to prevent unauthorized variations and loss of value for money.


15. Why must procurement officers avoid conflict of interest situations?

A. To maintain impartiality and public confidence
B. To increase procurement speed
C. To strengthen supplier loyalty
D. To reduce paperwork

Answer: A

Rationale: Avoiding conflicts of interest preserves objectivity, protects the integrity of procurement decisions, and maintains public confidence in the use of public resources.


16.  During tender clarification, one bidder contacts you privately requesting additional information. What is the correct action?

A. Share information verbally
B. Respond privately to the bidder
C. Ignore the request
D. Provide clarification in writing to all bidders simultaneously

Answer: D

Rationale: All clarifications must be shared equally with all bidders to preserve fairness and transparency.


17. You are part of an evaluation committee and realize you previously worked for one of the bidders. What should you do?

A. Keep silent to avoid delays
B. Continue but avoid voting
C. Declare the conflict of interest and withdraw from the evaluation
D. Influence scoring to appear neutral

Answer: C

Rationale: Declaring conflicts and recusing oneself protects the integrity and credibility of the procurement process.


18. Which factor is MOST critical when procuring safety-critical items for airline operations?

A. Lowest cost available
B. Supplier proximity
C. Compliance with required technical and safety standards
D. Fastest delivery regardless of quality

Answer: C

Rationale: In aviation-related procurement, compliance with technical and safety standards is paramount, as failure can compromise operational safety and regulatory compliance.


19. What is the PRIMARY consequence of poor procurement record management?

A. Increased supplier competition
B. Faster procurement cycles
C. Improved operational efficiency
D. Audit challenges and accountability gaps

Answer: D

Rationale: Poor record management weakens audit trails, increases the risk of non-compliance findings, and undermines accountability in public procurement.


20. During contract execution, a supplier consistently delays delivery without justification. What is the correct procurement response?

A. Ignore delays to preserve relationship
B. Enforce contract terms and apply remedies provided in the contract
C. Terminate contract immediately without process
D. Increase payment to motivate supplier

Answer: B

Rationale: Contract remedies exist to protect the organization and must be applied in a structured, lawful manner.


21. Why should procurement documents be standardized in public procurement?

A. To ensure consistency and legal compliance
B. To reduce competition
C. To favor experienced suppliers
D. To simplify evaluations unfairly

Answer: A

Rationale: Standardized documents ensure consistency, reduce ambiguity, and align procurement processes with legal and regulatory requirements, lowering dispute risks.


22. What is the MAIN purpose of supplier performance evaluation?

A. Penalizing suppliers
B. Identifying reliability and improvement areas
C. Eliminating new suppliers
D. Increasing contract prices

Answer: B

Rationale: Supplier performance evaluation helps organizations assess reliability, quality, and delivery performance, supporting informed decisions on future engagements.


23. Which procurement practice BEST supports accountability?

A. Informal approvals
B. Verbal instructions
C. Documented approvals at each stage
D. Emergency procurement as routine

Answer: C

Rationale: Documented approvals at each stage create traceability, enabling audits and ensuring procurement actions are authorized and justified.


24. Why should procurement officers understand basic financial principles?

A. To replace accountants
B. To approve budgets
C. To support cost control and expenditure monitoring
D. To prepare financial statements

Answer: C

Rationale: Understanding financial principles enables procurement officers to monitor expenditures, support budget discipline, and contribute to value-for-money outcomes.


25. What BEST demonstrates professional ethics in procurement?

A. Accepting supplier gifts
B. Delaying evaluations intentionally
C. Sharing confidential bid information
D. Acting impartially and declaring interests

Answer: B

Rationale: Professional ethics require impartial conduct and transparency; declaring interests and avoiding undue influence preserves integrity and public trust in procurement decisions.


26. In public procurement, what is the PRIMARY objective of preparing a detailed procurement specification?

A. To clearly define the organization’s requirements in an objective manner
B. To restrict participation to known suppliers
C. To speed up contract signing
D. To reduce the need for evaluation

Answer: A

Rationale: A detailed procurement specification defines technical, functional, and performance requirements objectively, enabling suppliers to submit responsive bids and ensuring fair competition while safeguarding value for money.


27. Why should a Procurement Officer II avoid splitting procurement requirements into smaller lots without justification?

A. It increases administrative workload
B. It may be used to circumvent approved procurement procedures
C. It delays supplier payments
D. It discourages local suppliers

Answer: B

Rationale: Artificial splitting of procurement requirements is prohibited because it can be used to avoid appropriate procurement methods and approvals, undermining transparency, legality, and accountability.


28. During bid evaluation, what does “responsiveness” of a bid mean?

A. The bidder has the lowest price
B. The bidder is locally registered
C. The bid meets all mandatory requirements of the tender document
D. The bid is submitted before other bidders

Answer: C

Rationale: A responsive bid fully complies with all mandatory technical, administrative, and commercial requirements stated in the tender documents, making it eligible for further evaluation.


29. Which document formally authorizes a supplier to deliver goods or services after contract award?

A. Goods Received Note
B. Delivery Note
C. Payment Voucher
D. Purchase Order

Answer: D

Rationale: A purchase order formally communicates acceptance of an offer and authorizes the supplier to deliver goods or services under agreed terms and conditions.


30. What is the MOST appropriate action when delivered goods do not meet contract specifications?

A. Accept goods to avoid delays
B. Pay the supplier and complain later
C. Store the goods for future use
D. Reject the goods and document non-conformity

Answer: D

Rationale: Goods that fail to meet specifications must be rejected and documented to protect the organization’s interests and enforce contractual obligations.

📘 Get the Full Aptitude Test Questions PDF through your  Gmail (Questions 1–200)

You’ve just accessed the first 30 questions. The full set of 200 expertly prepared Aptitude Test questions for Afisa Manunuzi Daraja la II (Procurement Officer II) at Air Tanzania Company Limited – ATCL. Is available, pay, and get access.

To get access to the full PDF, please make a payment of Tsh 10,000 to the LIPA numbers below:

Airtel Money LIPA Number: 13970429
Yas/Tigo LIPA Number: 18401500
M-Pesa WAKALA:  826910
CRDB Lipa TANQR : 11692089
Registered Name: Johnson Yesaya Mgelwa

After payment, please send a text message to notify us of your payment:

Contact Number: +255 628 729 934

⚠️ Important Notice

  • The PDF will be watermarked with your name and phone number and protected for personal use only.
  • Redistribution, sharing, screenshotting, or copying the contents is strictly prohibited. When you share unlawfully, your name and phone number are visible and easy to trace as you leaked a document to other third parties.
  • Legal action may be taken against the misuse of this material.

Thank you for supporting quality content. Best of luck in your interview preparation!